N.Y. Lien Law Section 11
Service of copy of notice of lien


Within five days before or thirty days after filing the notice of lien, the lienor shall serve a copy of such notice upon the owner, if a natural person, (a) by delivering the same to him personally, or if the owner cannot be found, to his agent or attorney, or

(b)

by leaving it at his last known place of residence in the city or town in which the real property or some part thereof is situated, with a person of suitable age and discretion, or

(c)

by registered or certified mail addressed to his last known place of residence, or

(d)

if such owner has no such residence in such city or town, or cannot be found, and he has no agent or attorney, by affixing a copy thereof conspicuously on such property, between the hours of nine o’clock in the forenoon and four o’clock in the afternoon; if the owner be a corporation, said service shall be made (i) by delivering such copy to and leaving the same with the president, vice-president, secretary or clerk to the corporation, the cashier, treasurer or a director or managing agent thereof, personally, within the state, or

(ii)

if such officer cannot be found within the state by affixing a copy thereof conspicuously on such property between the hours of nine o’clock in the forenoon and four o’clock in the afternoon, or

(iii)

by registered or certified mail addressed to its last known place of business. Failure to file proof of such a service with the county clerk within thirty-five days after the notice of lien is filed shall terminate the notice as a lien. Until service of the notice has been made, as above provided, an owner, without knowledge of the lien, shall be protected in any payment made in good faith to any contractor or other person claiming a lien.

Source: Section 11 — Service of copy of notice of lien, https://www.­nysenate.­gov/legislation/laws/LIE/11 (updated Sep. 22, 2014; accessed Apr. 13, 2024).

3
Mechanic’s lien on real property
4
Extent of lien
4–A
Insurance proceeds liable for demands
5
Liens under contracts for public improvements
6
Liens for labor on railroads
7
Liability for advance payments, collusive mortgages and incumbrances
8
Terms of contract may be demanded
9
Contents of notice of lien
10
Filing of notice of lien
11
Service of copy of notice of lien
11–A
Notice of completion and acceptance may be demanded
11–B
Copy of notice of lien to a contractor or subcontractor
11–C
Copy of notice of lien to a contractor or subcontractor with respect to public improvements liens
12
Notice of lien on account of public improvements
12–A
Amendment
13
Priority of liens
14
Assignment of lien
15
Assignments of contracts and orders to be filed
16
Assignment of contracts and orders for public improvement to be filed
17
Duration of lien
18
Duration of lien under contract for a public improvement
19
Discharge of lien for private improvement
20
Discharge of lien after notice of lien filed by payment of money into court
21
Discharge of lien for public improvement
21–A
Vacating lien for a public improvement, by order of court
22
Building loan contract
23
Construction of article
24
Enforcement of mechanic’s lien
25
Priority of liens and assignments under contracts for public improvements
26
Subordination of liens after agreement with owner
28
Lien of certain judgments postponed
29
Subordination of liens to subsequent mortgage
30
Subordination of notices of lis pendens
31
Discharge of liens on sale of real property
32
Certain liens and claims not to be affected
33
Certain sections not to apply to laborers’ liens
34
Waiver of lien
35
Waiver of arbitration
37
Bond to discharge all liens
38
Itemized statement may be required of lienor
39
Lien wilfully exaggerated is void
39–A
Liability of lienor where lien has been declared void on account of wilful exaggeration
39–C
Repossession of materials not used

Accessed:
Apr. 13, 2024

Last modified:
Sep. 22, 2014

§ 11’s source at nysenate​.gov

Link Style