Tex. Health & Safety Code Section 382.05195
Standard Permit


(a)

The commission may issue a standard permit for new or existing similar facilities if the commission finds that:

(1)

the standard permit is enforceable;

(2)

the commission can adequately monitor compliance with the terms of the standard permit; and

(3)

for permit applications for facilities subject to Sections 382.0518 (Preconstruction Permit)(a)-(d) filed before September 1, 2001, the facilities will use control technology at least as effective as that described in Section 382.0518 (Preconstruction Permit)(b). For permit applications filed after August 31, 2001, all facilities permitted under this section will use control technology at least as effective as that described in Section 382.0518 (Preconstruction Permit)(b).

(b)

The commission shall publish notice of a proposed standard permit in the Texas Register and in one or more statewide or regional newspapers designated by the commission by rule that will, in the commission’s judgment, provide reasonable notice throughout the state. If the standard permit will be effective for only part of the state, the notice shall be published in a newspaper of general circulation in the area to be affected. The commission by rule may require additional notice to be given. The notice must include an invitation for written comments by the public to the commission regarding the proposed standard permit and must be published not later than the 30th day before the date the commission issues the standard permit.

(c)

The commission shall hold a public meeting to provide an additional opportunity for public comment. The commission shall give notice of a public meeting under this subsection as part of the notice described in Subsection (b) not later than the 30th day before the date of the meeting.

(d)

If the commission receives public comment related to the issuance of a standard permit, the commission shall issue a written response to the comments at the same time the commission issues or denies the permit. The response must be made available to the public, and the commission shall mail the response to each person who made a comment.

(e)

The commission by rule shall establish procedures for the amendment of a standard permit and for an application for, the issuance of, the renewal of, and the revocation of an authorization to use a standard permit.

(f)

A facility authorized to emit air contaminants under a standard permit shall comply with an amendment to the standard permit beginning on the date the facility’s authorization to use the standard permit is renewed or the date the commission otherwise provides. Before the date the facility is required to comply with the amendment, the standard permit, as it read before the amendment, applies to the facility.

(g)

The adoption or amendment of a standard permit or the issuance, renewal, or revocation of an authorization to use a standard permit is not subject to Chapter 2001 (Administrative Procedure), Government Code.

(h)

The commission may adopt rules as necessary to implement and administer this section.

(i)

The commission may delegate to the executive director the authority to issue, amend, renew, or revoke an authorization to use a standard permit.

(j)

If a standard permit for a facility requires a distance, setback, or buffer from other property or structures as a condition of the permit, the determination of whether the distance, setback, or buffer is satisfied shall be made on the basis of conditions existing at the earlier of:

(1)

the date new construction, expansion, or modification of a facility begins; or

(2)

the date any application or notice of intent is first filed with the commission to obtain approval for the construction or operation of the facility.

(k)

An application for the issuance of a standard permit under this section for a concrete plant that performs wet batching, dry batching, or central mixing, including a permanent, temporary, or specialty concrete batch plant, as defined by the commission, must include a plot plan that clearly shows:

(1)

a distance scale;

(2)

a north arrow;

(3)

all property lines, emission points, buildings, tanks, and process vessels and other process equipment in the area in which the facility will be located;

(4)

at least two benchmark locations in the area in which the facility will be located; and

(5)

if the permit requires a distance, setback, or buffer from other property or structures as a condition of the permit, whether the required distance or setback will be met.
Added by Acts 1999, 76th Leg., ch. 406, Sec. 5, eff. Aug. 30, 1999.
Amended by:
Acts 2005, 79th Leg., Ch. 422 (S.B. 1740), Sec. 2, eff. September 1, 2005.
Acts 2021, 87th Leg., R.S., Ch. 159 (S.B. 952), Sec. 1, eff. September 1, 2021.

Source: Section 382.05195 — Standard Permit, https://statutes.­capitol.­texas.­gov/Docs/HS/htm/HS.­382.­htm#382.­05195 (accessed Apr. 20, 2024).

382.001
Short Title
382.002
Policy and Purpose
382.003
Definitions
382.004
Construction While Permit Amendment Application Pending
382.005
Exclusive Jurisdiction to Regulate Greenhouse Gas Emissions and Express Preemption of Local Regulations
382.011
General Powers and Duties
382.012
State Air Control Plan
382.013
Air Quality Control Regions
382.014
Emission Inventory
382.015
Power to Enter Property
382.016
Monitoring Requirements
382.017
Rules
382.018
Outdoor Burning of Waste and Combustible Material
382.019
Methods Used to Control and Reduce Emissions from Land Vehicles
382.020
Control of Emissions from Facilities that Handle Certain Agricultural Products
382.021
Sampling Methods and Procedures
382.022
Investigations
382.023
Orders
382.024
Factors in Issuing Orders and Determinations
382.025
Orders Relating to Controlling Air Pollution
382.026
Orders Issued Under Emergencies
382.027
Prohibition on Commission Action Relating to Air Conditions Existing Solely in Commercial and Industrial Facilities
382.028
Variances
382.029
Hearing Powers
382.030
Delegation of Hearing Powers
382.031
Notice of Hearings
382.032
Appeal of Commission Action
382.033
Contracts
382.034
Research and Investigations
382.035
Memorandum of Understanding
382.036
Cooperation and Assistance
382.037
Notice in Texas Register Regarding National Ambient Air Quality Standards for Ozone
382.040
Documents
382.041
Confidential Information
382.051
Permitting Authority of Commission
382.053
Prohibition on Issuance of Construction Permit for Lead Smelting Plant at Certain Locations
382.054
Federal Operating Permit
382.055
Review and Renewal of Preconstruction Permit
382.056
Notice of Intent to Obtain Permit or Permit Review
382.057
Exemption
382.058
Notice of and Hearing on Construction of Concrete Plant Under Permit by Rule, Standard Permit, or Exemption
382.059
Hearing and Decision on Permit Amendment Application of Certain Electric Generating Facilities
382.061
Delegation of Powers and Duties
382.062
Application, Permit, and Inspection Fees
382.063
Issuance of Emergency Order Because of Catastrophe
382.064
Initial Application Date
382.065
Certain Locations for Operating Concrete Crushing Facility Prohibited
382.066
Shipyard Facilities
382.068
Poultry Facility Odor
382.069
Texas Backup Power Package
382.085
Unauthorized Emissions Prohibited
382.111
Inspections
382.112
Recommendations to Commission
382.113
Authority of Municipalities
382.115
Cooperative Agreements
382.0145
Clean Fuel Incentive Surcharge
382.0161
Air Pollutant Watch List
382.0171
Alternative Fuels and Select-use Technologies
382.0172
International Border Areas
382.0173
Adoption of Rules Regarding Certain State Implementation Plan Requirements and Standards of Performance for Certain Sources
382.0175
Amount of Foreign Emissions in Nonattainment Areas
382.0191
Idling of Motor Vehicle
382.0195
Commercial Infectious Waste Incinerators
382.0201
Prohibition on Commission Rule Relating to Emissions from Certain Hospital or Medical Disinfectants
382.201
Definitions
382.202
Vehicle Emissions Inspection and Maintenance Program
382.203
Vehicles Subject to Program
382.204
Remote Sensing Program Component
382.0205
Special Problems Related to Air Contaminant Emissions
382.205
Inspection Equipment and Procedures
382.206
Collection of Data
382.207
Inspection Stations
382.208
Attainment Program
382.209
Low-income Vehicle Repair Assistance, Retrofit, and Accelerated Vehicle Retirement Program
382.210
Implementation Guidelines and Requirements
382.211
Local Advisory Panel
382.212
Emissions Reduction Credit
382.213
Disposition of Retired Vehicle
382.214
Sale of Vehicle with Intent to Defraud
382.0215
Assessment of Emissions Due to Emissions Events
382.215
Sale of Vehicle Not Required
382.0216
Regulation of Emissions Events
382.216
Incentives for Voluntary Participation in Vehicle Emissions Inspection and Maintenance Program
382.218
Required Participation by Certain Counties
382.219
Purchase of Replacement Vehicle
382.220
Use of Funding for Local Initiative Projects
382.0275
Commission Action Relating to Residential Water Heaters
382.0291
Public Hearing Procedures
382.301
Definitions
382.302
Inspection and Maintenance Program
382.0335
Air Control Account
382.401
Alternative Leak Detection Technology
382.451
Development of Federal Greenhouse Gas Reporting Rule
382.452
Voluntary Actions Inventory
382.501
Definitions
382.502
Rules
382.503
Study
382.504
Contract for Necessary Infrastructure and Operation
382.505
Acceptance of Carbon Dioxide for Storage
382.506
Measuring, Monitoring, and Verification
382.507
Ownership of Carbon Dioxide
382.508
Liability
382.509
Rates for Transportation
382.510
Annual Report
382.0511
Permit Consolidation and Amendment
382.0512
Modification of Existing Facility
382.0513
Permit Conditions
382.0514
Sampling, Monitoring, and Certification
382.0515
Application for Permit
382.0516
Notice to State Senator, State Representative, and Certain Local Officials
382.0517
Determination of Administrative Completion of Application
382.0518
Preconstruction Permit
382.0519
Voluntary Emissions Reduction Permit
382.0541
Administration and Enforcement of Federal Operating Permit
382.0542
Issuance of Federal Operating Permit
382.0543
Review and Renewal of Federal Operating Permit
382.551
Substitutes for Hydrofluorocarbon Refrigerants Applicable to Commercial or Residential Buildings or Construction
382.0561
Federal Operating Permit: Hearing
382.0562
Notice of Decision
382.0563
Public Petition to the Administrator
382.0564
Notification to Other Governmental Entities
382.0565
Clean Coal Project Permitting Procedure
382.0566
Advanced Clean Energy Project Permitting Procedure
382.0567
Proof that Technology Is Commercially Feasible Not Required
382.0591
Denial of Application for Permit
382.0621
Operating Permit Fee
382.0622
Clean Air Act Fees
382.05101
De Minimis Air Contaminants
382.05102
Permitting Authority of Commission
382.05155
Expedited Processing of Application
382.05181
Permit Required
382.05182
Notice of Shutdown
382.05183
Existing Facility Permit
382.05184
Small Business Stationary Source Permit
382.05185
Electric Generating Facility Permit
382.05186
Pipeline Facilities Permits
382.05191
Emissions Reduction Permits: Notice and Hearing
382.05192
Review and Renewal of Emissions Reduction and Multiple Plant Permits
382.05193
Emissions Permits Through Emissions Reduction
382.05194
Multiple Plant Permit
382.05195
Standard Permit
382.05196
Permits by Rule
382.05197
Multiple Plant Permit: Notice and Hearing
382.05198
Standard Permit for Certain Concrete Plants
382.05199
Standard Permit for Certain Concrete Batch Plants: Notice and Hearing
382.051865
Stationary Natural Gas Engines Used in Combined Heating and Power System
382.051866
Emissions Reductions Incentives Account
382.051961
Permit for Certain Oil and Gas Facilities
382.051962
Authorization for Planned Maintenance, Start-up, or Shutdown Activities Relating to Certain Oil and Gas Facilities
382.051963
Amendment of Certain Permits
382.051964
Aggregation of Facilities
382.051985
Standard Permit for Certain Temporary Concrete Plants for Public Works