Tex. Gov't Code Section 2252.032
Retainage


(a)

A governmental entity shall:

(1)

include in each public works contract a provision that establishes the circumstances under which:

(A)

the public works project that is the subject of the contract is considered substantially complete; and

(B)

the governmental entity may release all or a portion of the retainage for:
(i)
substantially completed portions of the project; or
(ii)
fully completed and accepted portions of the project;

(2)

maintain an accurate record of accounting for:

(A)

the retainage withheld on periodic contract payments; and

(B)

the retainage released to the prime contractor for a public works contract; and

(3)

for a public works contract described by Subsection (c), pay any remaining retainage described by Subdivision (2)(A) and the interest earned on the retainage to the prime contractor on completion of the work required to be performed under the contract.

(b)

Except as provided by Subsection (i):

(1)

if the total value of a public works contract is less than $5 million, a governmental entity may not withhold retainage in an amount that exceeds 10 percent of the contract price and the rate of retainage may not exceed 10 percent for any item in a bid schedule or schedule of values for the project, including materials and equipment delivered on site to be installed;

(2)

if the total value of a public works contract is $5 million or more, a governmental entity may not withhold retainage in an amount that exceeds five percent of the contract price and the rate of retainage may not exceed five percent for any item in a bid schedule or schedule of values for the project, including materials and equipment delivered on site to be installed; and

(3)

if a public works contract relates to the construction or maintenance of a dam, as that term is defined by Section 423.0045 (Offense: Operation of Unmanned Aircraft over Critical Infrastructure Facility), regardless of the total value of the contract, a governmental entity may not withhold retainage in an amount that exceeds 10 percent of the contract price and the rate of retainage may not exceed 10 percent for any item in a bid schedule or schedule of values for the project, including materials and equipment delivered on site to be installed.

(c)

For a competitively awarded contract with a value of $10 million or more, and for a contract that was awarded using a method other than competitive bidding, a governmental entity and prime contractor may agree to deposit in an interest-bearing account the retainage withheld on periodic contract payments.

(d)

If, for the purpose of fulfilling an obligation of a prime contractor under a public works contract, the prime contractor enters into a subcontract:

(1)

the prime contractor may not withhold from a subcontractor a greater percentage of retainage than the percentage that may be withheld from the prime contractor by the governmental entity under the contract; and

(2)

a subcontractor who enters into a contract with another subcontractor to provide labor or materials under the contract may not withhold from that subcontractor a greater percentage of retainage than the percentage that may be withheld from the subcontractor as determined under Subdivision (1).

(e)

A governmental entity may not withhold retainage:

(1)

after completion of the work required to be performed under the contract by the prime contractor, including during the warranty period; or

(2)

for the purpose of requiring the prime contractor, after completion of the work required to be performed under the contract, to perform work on manufactured goods or systems that were:

(A)

specified by the designer of record; and

(B)

properly installed by the contractor.

(f)

On application to a governmental entity for final payment and release of retainage, the governmental entity may withhold retainage if there is a bona fide dispute between the governmental entity and the prime contractor and the reason for the dispute is that labor, services, or materials provided by the prime contractor, or by a person under the direction or control of the prime contractor, failed to comply with the express terms of the contract or if the surety on any outstanding surety bond executed for the contract does not agree to the release of retainage. The governmental entity must provide to the prime contractor written notice of the basis on which the governmental entity is withholding retainage under this subsection. If there is no bona fide dispute between the governmental entity and the prime contractor and neither party is in default under the contract, the prime contractor is entitled to:

(1)

cure any noncompliant labor, services, or materials; or

(2)

offer the governmental entity a reasonable amount of money as compensation for any noncompliant labor, services, or materials that cannot be promptly cured.

(g)

A governmental entity is not required to accept a prime contractor’s offer of compensation under Subsection (f)(2).

(h)

Subsection (f) may not be construed to limit either the governmental entity’s or prime contractor’s right to pursue any remedy available under the express terms of the public works contract or other applicable law.

(i)

For purposes of this subsection, a project is considered formally approved if the project is the subject of a resolution approving an application for financial assistance adopted by the Texas Water Development Board before September 1, 2019, for any part of the project’s financing. Subsection (b) of this section does not apply to a governmental entity that receives financial assistance under Section 15.432 (Fund) or 15.472 (Fund), Water Code, for a project that is formally approved by the Texas Water Development Board or to a governmental entity that is a wholesale water supplier that supplies water to customers in 10 or more counties and is governed by Chapter 49 (Provisions Applicable to All Districts), Water Code. A governmental entity described by this subsection shall deposit in an interest-bearing account the retainage withheld under a public works contract that provides for retainage that exceeds five percent of the periodic contract payments.

(j)

This section may not be construed as affecting a governmental entity’s ability to retain certain amounts due under a contract as required by Chapter 2258 (Prevailing Wage Rates).
Added by Acts 1993, 73rd Leg., ch. 268, Sec. 1, eff. Sept. 1, 1993.
Amended by:
Acts 2021, 87th Leg., R.S., Ch. 635 (H.B. 692), Sec. 3, eff. June 15, 2021.

Source: Section 2252.032 — Retainage, https://statutes.­capitol.­texas.­gov/Docs/GV/htm/GV.­2252.­htm#2252.­032 (accessed May 18, 2024).

Accessed:
May 18, 2024

§ 2252.032’s source at texas​.gov