A reclamation plan submitted as part of a permit application shall include, in sufficient detail to demonstrate that reclamation required by this chapter can be accomplished, a statement that:

(1)

identifies land subject to the surface coal mining operation over the estimated life of the operation and the size, sequence, and timing of any subareas for which it is anticipated that individual permits for surface coal mining will be sought;

(2)

describes the condition of the land to be covered by the permit before any mining, including:

(A)

the uses existing at the time of the application and, if the land has a history of mining, the uses that preceded any mining;

(B)

the capability of the land before any mining to support a variety of uses, considering soil and foundation characteristics, topography, vegetative cover, and, if applicable, a soil survey prepared under Section 134.052 (Contents of Permit Application)(a)(16);

(C)

the productivity of the land before mining, including appropriate classification as prime farmland; and

(D)

if the land is classified as prime farmland, the average yield of food, fiber, forage, or wood products obtained from the land under high levels of management;

(3)

describes the proposed use of the land after reclamation,including:

(A)

a discussion of the utility and capacity of the reclaimed land to support a variety of alternative uses and the relationship of those uses to existing land uses; and

(B)

the comments of state and local governments or agencies of state or local government that must approve or authorize the proposed use of the land after reclamation;

(4)

describes in detail how the proposed postmining land use is to be achieved and the necessary support activities that may be needed to achieve that use;

(5)

specifies the engineering techniques proposed to be used in mining and reclamation and describes the major equipment;

(6)

includes a plan for the control of surface water drainage and water accumulation;

(7)

includes, if appropriate, a plan for backfilling, soil stabilization and compacting, grading, and appropriate revegetation;

(8)

includes a plan for soil reconstruction, replacement, and stabilization under the performance standards in Section 134.092 (Performance Standards)(a)(7) for land identified as prime farmland under Section 134.052 (Contents of Permit Application)(a)(16);

(9)

estimates the cost for each acre of the reclamation, including a statement as to how the permit holder plans to comply with each requirement in Sections 134.091 (Operations Required to Meet Performance Standards) through 134.109 (Variance from Requirement to Restore Contour);

(10)

describes the consideration given to maximizing the use and conservation of the solid fuel resource being recovered so that reaffecting the land in the future can be minimized;

(11)

provides an estimated timetable for accomplishing each major step in the reclamation plan;

(12)

describes the consideration given to making the surface mining and reclamation operations consistent with surface owner plans and applicable land use plans and programs;

(13)

identifies the steps to be taken to comply with applicable air and water quality laws, rules, and regulations and any applicable health and safety standards;

(14)

describes the consideration given to developing the reclamation plan in a manner consistent with local physical, environmental, and climatological conditions;

(15)

contains the results of test borings the applicant has made at the permit area or other equivalent information in a form satisfactory to the commission, including:

(A)

the location of subsurface water; and

(B)

an analysis of the chemical properties of the coal and overburden that can be expected to adversely affect the environment;

(16)

identifies:

(A)

any land contiguous to the area to be covered by the permit, or any interest or option on an interest in the contiguous land, held by the applicant; and

(B)

any pending bid by the applicant on an interest in the contiguous land; and

(17)

describes in detail the measures to be taken during the mining and reclamation process to assure the protection of:

(A)

the quality of surface-water systems and groundwater systems, both on and off the mine site, from adverse effects of the mining and reclamation process;

(B)

the rights of present users to surface-water systems and groundwater systems, both on and off the mine site; and

(C)

the quantity of surface-water systems and groundwater systems, both on and off the mine site, from adverse effects of the mining and reclamation process, or to provide alternative sources of water where the protection of quantity cannot be assured.
Added by Acts 1995, 74th Leg., ch. 76, Sec. 12.02(a), eff. Sept. 1, 1995.

Source: Section 134.041 — Reclamation Plan, https://statutes.­capitol.­texas.­gov/Docs/NR/htm/NR.­134.­htm#134.­041 (accessed Apr. 29, 2024).

134.001
Short Title
134.002
Findings and Declaration of Policy
134.003
Purposes
134.004
Definitions
134.005
Exemptions
134.006
Water Rights
134.007
Conflict of Interest
134.008
Applicability to Governmental Units
134.011
General Authority of Commission
134.012
Jurisdiction of Commission over Surface Coal, Iron Ore, and Iron Ore Gravel Mining and Reclamation Operations
134.013
Rulemaking and Permitting
134.014
Coal Exploration Operations
134.015
Surface Effects of Underground Mining
134.016
Development of Process for Designating Areas Unsuitable for Surface Coal Mining
134.017
Petition for Designation
134.018
Hearing on Designation
134.019
Commission Statement
134.020
Designation of Area as Unsuitable for Surface Coal Mining
134.021
Integration with Land Use Planning and Regulation Processes
134.022
Prohibition on Surface Coal Mining in Certain Areas
134.023
Cooperative Agreements with Federal Government
134.024
Experimental Practices
134.025
Certification of Blasters
134.026
Monitoring, Reporting, and Inspections
134.027
Monitoring of Operations that Affect Aquifers
134.028
Inspection Procedure
134.029
Procedure on Detection of Violation
134.030
Rules Regarding Monitoring, Reporting, and Inspections
134.031
Confidentiality
134.032
Determination Regarding Prime Farmland
134.041
Reclamation Plan
134.042
Blasting Plan
134.051
Permit Required for Operation
134.052
Contents of Permit Application
134.053
Liability Insurance Policy
134.054
Application Fees
134.055
Annual Fees
134.056
Small Mine Exemption
134.057
Public Inspection of Application
134.058
Notice by Applicant
134.059
Notification by Commission
134.060
Comments
134.061
Written Objections
134.062
Request for Public Hearing
134.063
Notice of Approval or Denial
134.064
Procedure
134.065
Permit Approval or Denial
134.066
Written Findings Required
134.067
Determination of Ownership
134.068
Schedule of Notices of Violations
134.069
Effect of Past or Present Violation
134.070
Permit for Mining on Prime Farmland
134.071
Term
134.072
Termination on Failure to Begin Operations
134.073
Successor in Interest
134.074
Right to Renewal
134.075
Application for and Issuance of Renewal
134.076
Extension of Permit Area
134.077
Term of Renewal Permit
134.078
Time Limit for Renewal Application
134.079
Application for Permit Revision
134.080
Approval of Permit Revision
134.081
Guidelines for Revision
134.082
Commission Requirement of Permit Revision or Modification
134.083
Transfer of Permit
134.084
Suspension or Rescission of Improvidently Issued Permit
134.085
Review Periods for New Permits, Renewals, and Revisions
134.091
Operations Required to Meet Performance Standards
134.092
Performance Standards
134.093
Backfilling, Grading, and Compacting: Insufficient Overburden
134.094
Backfilling, Grading, and Compacting: Sufficient Overburden
134.095
Maintenance of Topsoil or Other Strata
134.096
Specifications for Soil Removal, Storage, Replacement, and Reconstruction
134.097
Removal, Storage, and Replacement of Soil and Overburden Without Regard to Soil Horizons
134.098
Prohibition on Augering
134.099
Certification of Siltation Structure
134.100
Proximity of Mine to Underground Mines: Exception
134.101
Rules Regarding Use of Explosives
134.102
Variance to Permit Underground Mining Operations Before Reclamation
134.103
Use of Introduced Species for Revegetation
134.104
Responsibility for Revegetation: Area of Low Precipitation
134.105
Responsibility for Revegetation: Long-term Intensive Agricultural Postmining Use
134.106
Spoil Disposal
134.107
Permit Without Regard to Requirement to Restore to Approximate Original Contour
134.108
Steep Slope Surface Coal Mining
134.109
Variance from Requirement to Restore Contour
134.110
Water Supply Replacement
134.121
Performance Bond Requirement
134.122
Amount of Bond
134.123
Bond Without Surety
134.124
Alternative to Bonding Program
134.125
Extent of Liability Under Bond
134.126
Security for Bond
134.127
Adjustment of Amount of Bond or Deposit
134.128
Application for Release of Bond or Deposit
134.129
Notice
134.130
Inspection and Evaluation
134.131
Release of Bond or Deposit
134.132
Notice to Permit Holder of Decision to Approve or Disapprove Release
134.133
Notice to County Judge
134.134
Objections to Release
134.141
Fund Participation
134.142
Eligibility of Land and Water
134.143
Right of Entry
134.144
Reclamation by Commission
134.145
Acquisition
134.146
Title
134.147
Cost of Land
134.148
Sale of Acquired Land
134.149
Hearing on Sale
134.150
Lien
134.151
Hearing on Lien
134.152
Emergency Powers
134.161
Condition, Practice, or Violation Creating Imminent Danger or Causing Imminent Harm
134.162
Violation Not Creating Imminent Danger or Causing Imminent Harm
134.163
Term of Cessation Order
134.164
Continuous Violation
134.165
Form of Notice or Order
134.166
Modification, Vacation, or Termination of Notice of Order
134.167
Expiration of Notice or Order
134.168
Application for Commission Review of Notice or Order
134.169
Investigation and Hearing on Application for Review
134.170
Commission Findings and Decision
134.171
Request for Temporary Relief
134.172
Assessment of Costs Incurred in Administrative Proceeding or Judicial Review
134.173
Civil Action
134.174
Administrative Penalty for Violation of Permit Condition of This Chapter
134.175
Penalty Assessment Procedure
134.176
Payment of Penalty
134.177
Administrative Penalty for Failing to Correct Violation for Which Citation Has Been Issued
134.178
Recovery of Administrative Penalty
134.179
Criminal Penalty for Wilful and Knowing Violation
134.180
Criminal Penalty for False Statement, Representation, or Certification
134.181
Penalty for Director, Officer, or Agent of Corporation
134.182
Citizen Suit
134.183
Notice to Commission Before Bringing Suit
134.184
Venue
134.185
Intervention by Commission
134.186
Costs of Suit
134.187
Rights Under Other Law
134.188
Defense

Accessed:
Apr. 29, 2024

§ 134.041’s source at texas​.gov