Tex. Water Code Section 27.073
Financial Responsibility


(a)

A person to whom an injection well permit is issued may be required by the commission or railroad commission to maintain a performance bond or other form of financial security to ensure that:

(1)

an abandoned injection well is properly plugged; or

(2)

funds are available for plugging, postinjection site care, and closure of an anthropogenic carbon dioxide injection well subject to Subchapter C-1.

(a-1)

Notwithstanding Subsection (a), a person to whom an in situ uranium mining injection well, monitoring well, or production well permit is issued shall be required by the commission to maintain a performance bond or other form of financial security to ensure that an abandoned well is properly plugged.

(b)

Each state agency is authorized to receive funds as the beneficiary of a financial responsibility mechanism established under this section for the proper plugging of an injection well. Each state agency is authorized to expend such funds from a financial responsibility mechanism for the plugging of wells covered by that mechanism.

(b-1)

The railroad commission is authorized to receive funds as the beneficiary of a financial responsibility mechanism established under this chapter for the proper management of an anthropogenic carbon dioxide injection well or geologic storage facility. The funds shall be deposited to the credit of the anthropogenic carbon dioxide storage trust fund established under Section 121.003 (Anthropogenic Carbon Dioxide Storage Trust Fund), Natural Resources Code.

(c)

If liability insurance is required of an applicant, the applicant may not use a claims made policy as security unless:

(1)

the policy provides for a right of extension by the insured upon cancellation or nonrenewal of the policy by the insurance company;

(2)

the applicant places in escrow as provided by the commission an amount sufficient to enable the commission to exercise the right under the policy to purchase an extension of the policy from the date of cancellation or expiration of the policy that is reasonable in light of the degree and duration of the risks; and

(3)

the applicant provides the commission with a limited power of attorney by which the commission is given an irrevocable power to exercise the applicant’s right under the policy to purchase such an extension of the policy.

(d)

In addition to other forms of financial security authorized by the rules of the commission, the commission may authorize an applicant to use the letter of credit form of financial security if either the issuing institution or another institution which guarantees payment under the letter:

(1)

is a bank chartered by the state or by the federal government;

(2)

is federally insured and its financial practices are regulated by the state or federal government; and

(3)

is solvent and is not in receivership or owned or controlled by an entity that is insolvent or in receivership.
Added by Acts 1981, 67th Leg., p. 3161, ch. 830, Sec. 1, eff. June 17, 1981. Amended by Acts 1985, 69th Leg., ch. 795, Sec. 1.120, eff. Sept. 1, 1985; Acts 1987, 70th Leg., ch. 638, Sec. 6, eff. Sept. 1, 1987; Acts 1989, 71st Leg., ch. 1234, Sec. 2, eff. Aug. 28, 1989.
Amended by:
Acts 2007, 80th Leg., R.S., Ch. 1118 (H.B. 3838), Sec. 7, eff. September 1, 2007.
Acts 2009, 81st Leg., R.S., Ch. 224 (S.B. 1387), Sec. 5, eff. September 1, 2009.
Acts 2021, 87th Leg., R.S., Ch. 460 (H.B. 1284), Sec. 14, eff. June 9, 2021.

Source: Section 27.073 — Financial Responsibility, https://statutes.­capitol.­texas.­gov/Docs/WA/htm/WA.­27.­htm#27.­073 (accessed May 11, 2024).

27.001
Short Title
27.002
Definitions
27.003
Policy and Purpose
27.011
Permit from Commission
27.012
Application for Permit
27.013
Information Required of Applicant
27.014
Application Fee
27.015
Letter from Railroad Commission
27.016
Inspection of Well Location
27.017
Recommendations from Other Entities
27.018
Hearing on Permit Application
27.019
Rules, Etc
27.020
Mining of Sulfur
27.021
Permit for Disposal of Brine from Desalination Operations or of Drinking Water Treatment Residuals in Class I Injection Wells
27.023
Jurisdiction over in Situ Uranium Application Development and Operations
27.024
Sharing of Geologic, Hydrologic, and Water Quality Data
27.025
General Permit Authorizing Use of Class I Injection Well to Inject Nonhazardous Brine from Desalination Operations or Nonhazardous Drinking Water Treatment Residuals
27.026
Dual Authorization of Injection Wells to Inject Nonhazardous Brine from Desalination Operations or Nonhazardous Drinking Water Treatment Residuals
27.031
Permit from Railroad Commission
27.032
Information Required of Applicant
27.033
Letter of Determination
27.034
Railroad Commission Rules, Etc
27.035
Jurisdiction over in Situ Recovery of Tar Sands
27.036
Jurisdiction over Brine Mining
27.037
Jurisdiction over Closed-loop Geothermal Injection Wells
27.040
Definition
27.041
Jurisdiction
27.042
Applicability
27.043
Permit from Railroad Commission
27.044
Information Required of Applicant
27.045
Fees
27.046
Letter of Determination from Railroad Commission
27.047
Rules
27.048
Consistency with and Implementation of Federal Requirements
27.049
Memorandum of Understanding
27.050
Financial Responsibility
27.051
Issuance of Permit
27.052
Copies of Permit
27.053
Record of Strata
27.054
Electric or Drilling Log
27.055
Casing Requirements
27.056
Factors in Setting Casing Depth
27.071
Power to Enter Property
27.072
Power to Examine Records
27.073
Financial Responsibility
27.101
Civil Penalty
27.102
Injunction, Etc
27.103
Procedure
27.104
Effect of Permit on Civil Liability
27.105
Criminal Fines
27.151
Definitions
27.152
Jurisdiction
27.153
Authorization for Use of Class V Injection Wells
27.154
Technical Standards
27.155
Reporting of Injection and Recovery Volumes
27.156
Reporting of Water Quality Data
27.157
Other Laws Not Affected
27.201
Definitions
27.202
Jurisdiction
27.203
Authorization for Use of Class V Injection Wells
27.204
Technical Standards
27.205
Reporting of Injection Volumes
27.206
Reporting of Water Quality Data
27.207
Other Laws Not Affected
27.0321
Application Fee
27.0461
Letter of Determination from Commission
27.0511
Conditions of Certain Permits
27.0513
Area Permits and Production Areas for Uranium Mining
27.0515
Facilities Required to Obtain Federal Approval
27.0516
Permits for Injection Wells that Transect or Terminate in Portion of Edwards Aquifer Within External Boundaries of Barton Springs-edwards Aquifer Conservation District
27.1011
Administrative Penalty
27.1012
Penalty Assessment Procedure
27.1013
Payment of Penalty
27.1014
Recovery of Penalty

Accessed:
May 11, 2024

§ 27.073’s source at texas​.gov